PracticeBARFree practice exam

BAR · Business Analysis · 6 practice questions

Capital Rationing: Choose the Highest-NPV Project Bundle

Under a hard budget, choose the feasible combination of whole projects with the highest total NPV. Below: a step-by-step example showing why profitability index and IRR rankings can select the wrong projects.

The ruleFor independent, indivisible projects under a hard capital budget, compare all feasible combinations and choose the highest combined NPV. Profitability index is a screening aid, not the final selection rule.

Try one first

North Co. has a Year 1 capital budget of $750,000 for three independent projects. Each project is indivisible, and North may accept any combination of projects that does not exceed the budget. All three projects have similar risk, and the NPVs below were computed using the appropriate required rate of return. Assume no constraints other than the stated capital budget.
ProjectInitial InvestmentNPVPIIRR
Project A$450,000$100,0001.2214%
Project B$400,000$94,0001.2415%
Project C$300,000$69,0001.2316%
Which choice is best supported?
Hint

List all project combinations that fit within $750,000, compute each bundle's total NPV, and choose the highest.

Step by step

  1. Lock down the constraints

    North Co. has a $750,000 capital budget for three independent, indivisible projects of similar risk. Accept only whole projects, and do not exceed the budget.

  2. Read the project data

    A costs $450,000, with NPV $100,000, PI 1.22, and IRR 14%; B costs $400,000, with NPV $94,000, PI 1.24, and IRR 15%. C costs $300,000, with NPV $69,000, PI 1.23, and IRR 16%; all NPVs were computed at the appropriate required return.

  3. Remove over-budget combinations

    A plus B costs $850,000, so reject that combination. All three cost $1,150,000, so reject that combination too.

  4. List every feasible choice

    The feasible choices are none, A, B, C, A plus C, and B plus C. Their total NPVs are $0, $100,000, $94,000, $69,000, $169,000, and $163,000, respectively.

  5. Choose the highest total NPV

    A plus C costs $750,000 and produces $169,000 of total NPV, exceeding B plus C by $6,000. Choose A and C because they maximize feasible NPV, not because they spend the full budget.

  6. Check the ranking shortcuts

    PI ranking points to B and C, but that pair produces only $163,000 of NPV. C's highest IRR does not justify choosing it alone, and A's highest standalone NPV does not justify stopping at A.

Key points

  • Remember: Compare bundles by total dollar value, not individual projects by percentage return.
  • An NPV computed at the required return already accounts for that return.
  • A positive NPV makes a project attractive, but does not guarantee selection under a budget.
  • Using the full budget is not the objective; maximizing feasible total NPV is.

How the exam traps you

  • Pick B and C because they have the two highest profitability indexes. Their $163,000 combined NPV is below A and C's $169,000.
  • Pick C alone because its 16% IRR is highest. C alone adds $69,000, not the $169,000 available from A and C.
  • Pick A and B because their combined NPV is highest among the pairs. Their $850,000 outlay exceeds the $750,000 cap.

5 more, each from a different angle

0 of 5 answered · 0 correct

Question 2

North Co. has a Year 1 capital budget of $900,000 and may not partially fund, delay, or abandon any accepted project. Each project is independent, equally risky, and would begin immediately if accepted. All cash flow amounts below are already present values using North's required rate of return. Ignore qualitative factors, and assume all tax effects are already reflected in the amounts given. Project Alpha: requires $500,000 for equipment and $100,000 of initial working capital. Present value of operating cash inflows is $690,000, and present value of end-of-project salvage plus working-capital recovery is $70,000. A $20,000 feasibility study relating to Alpha was paid last year. Project Beta: requires $450,000 for equipment and a $50,000 nonrefundable software license. Present value of cash inflows is $640,000. Project Gamma: requires $300,000 for equipment and $100,000 of initial working capital. Present value of operating cash inflows is $430,000, and present value of end-of-project salvage plus working-capital recovery is $45,000. If North's objective is to maximize value subject to the funding limit, which project selection is best?
Hint

First identify relevant initial outlays and ignore sunk costs. Then compute each project's NPV and compare only combinations that fit within the Year 1 funding cap.

Question 3

A company has a 20X6 capital budget of $1,000,000 for independent projects. Each project is indivisible, the company may accept any combination of projects within the budget, there are no synergies or conflicts among projects, and any unused funds have no alternative positive-NPV use. The following measures were computed using the appropriate required return for each project: Project A: outlay $250,000; NPV $40,000; PI 1.16; IRR 14%. Project B: outlay $250,000; NPV $35,000; PI 1.14; IRR 15%. Project C: outlay $500,000; NPV $95,000; PI 1.19; IRR 18%. Project D: outlay $750,000; NPV $135,000; PI 1.18; IRR 16%. Which investment decision is best supported?
Hint

First decide which metric should govern the portfolio choice under a fixed budget when projects cannot be split, then compare total value across feasible combinations.

Question 4

Mercury Co. has a hard Year 1 capital budget of $1,300,000 and is evaluating four independent, indivisible projects. Each project's NPV was computed using Mercury's required rate of return. Any unused portion of the budget will remain idle in cash, and there are no other positive-NPV projects available. The data are: Project A: initial investment $400,000; NPV $72,000; IRR 18%; profitability index 1.18. Project B: initial investment $700,000; NPV $112,000; IRR 16%; profitability index 1.16. Project C: initial investment $500,000; NPV $90,000; IRR 17%; profitability index 1.18. Project D: initial investment $900,000; NPV $153,000; IRR 15%; profitability index 1.17. Which portfolio is the most appropriate selection if Mercury's objective is to maximize firm value?
Hint

Do not rank projects only by IRR or profitability index. First determine the decision rule that best matches shareholder-value maximization under a fixed budget and indivisible projects, then compare only feasible portfolios.

Question 5

A company has a $400,000 capital budget for the coming year and is evaluating three independent projects. NPVs below are computed at the company's WACC of 10%; projects may be accepted in any combination as long as total initial investment does not exceed $400,000 and fractional projects are not allowed. Project A: initial investment $250,000; IRR 14%; NPV $60,000. Project B: initial investment $200,000; IRR 22%; NPV $50,000. Project C: initial investment $150,000; IRR 13%; NPV $35,000. Assuming the firm's objective is to maximize total NPV, which combination should the CFO recommend?
Hint

List every feasible project combination that fits the $400,000 limit and compare their total NPVs, do not rely solely on IRR or a greedy profitability-index ranking.

Question 6

Lark Co. has a hard Year 1 capital budget of $1,000,000 for new investments. Projects are indivisible, independent, and of comparable risk. All cash flow patterns are conventional, and no additional financing is available. Lark is evaluating the following projects using a 12% required return:
ItemDetails
Atlasinitial investment $700,000; NPV $126,000; IRR 17.2%; profitability index 1.18
Beaconinitial investment $600,000; NPV $108,000; IRR 18.0%; profitability index 1.18
Crestinitial investment $400,000; NPV $84,000; IRR 16.4%; profitability index 1.21
If Lark's objective is to maximize firm value subject to the capital limit, which alternative should be classified as the financially preferred feasible choice for Year 1?
Hint

First identify every feasible project set under the $1,000,000 cap. Then apply the value-maximization criterion to the feasible set, not just to the individual project with the strongest single metric.

Drill all 123 Investment alternatives using financial valuation decision models questionsMixed across every rule in the topic, so you have to spot which one applies. That is how the exam does it.

Common questions

How do you choose projects under capital rationing?

List the combinations that fit the budget, then compare their total NPVs. Here, A and C produce the highest feasible total NPV: $169,000.

Why can profitability index give the wrong capital rationing answer?

PI measures value relative to investment, not total dollar value. With whole projects, the higher-PI pair B and C creates less total NPV than A and C.

Should you choose the project with the highest IRR?

Not when the objective is the highest total NPV under a hard budget. C has the highest IRR, but accepting A with C creates more value than C alone.

Practice BAR like the real exam

The free ChatCPA simulator: real exam layout, timed testlets, starting with a question on this topic. No account needed to start.

Open the free simulator →

More on Investment alternatives using financial valuation decision models

All Investment alternatives using financial valuation decision models practice →

Questions from the ChatCPA bank of 17,658 CPA exam questions, each with a written reason for every wrong answer. ChatCPA is built by Nicholas Miller, CPA (Oregon #14907). How these pages are made. Spot an error? Tell us.