AUD · Assessing Risk and Developing a Planned Response · 6 practice questions
Audit Planning Sequence Under AU-C 300
Complete preliminary engagement activities first, then develop current-year planning that guides further audit procedures. Below: follow a recurring client's new ERP system through initial strategy, materiality, risk assessment planning, and later revisions.
Try one first
Hint
Consider when each activity typically occurs in the audit lifecycle, during acceptance/planning or during evidence gathering and conclusion.
Answer D. A formal written management representation letter is a concluding audit document obtained at or near the end of fieldwork as part of final evidence gathering. Planning activities instead include obtaining management's agreement to responsibilities (engagement letter), setting preliminary materiality and the overall audit strategy, and communicating with the predecessor auditor when applicable.
Why not A: Tempting because it mentions a written document and management responsibilities (which sounds similar to a representation), but obtaining management's acceptance of responsibilities via the engagement letter is an acceptance/planning activity performed early, not an exception.
Why not B: Tempting because contact with a predecessor auditor may raise later issues, but the communication itself is part of client acceptance/continuance and early planning considerations, not something excluded from planning.
Why not C: Tempting because materiality and strategy are refined later, yet establishing preliminary materiality and an overall audit strategy is a central planning task and therefore not an exception.
Step by step
- Resolve preliminary engagement matters
Harbor is a recurring audit client with a new ERP system and a tight deadline. Address current-year continuance and ethical requirements, including independence, at the outset rather than proceeding with unresolved matters.
- Confirm engagement terms
Consider whether Harbor's changed circumstances require revised engagement terms or a reminder of existing terms, and resolve any needed agreement before significant procedures. A new engagement letter is not automatically required every year.
- Establish the initial strategy
With the engagement partner and key team members involved, establish and document the audit's scope, timing, and direction, including resource needs for Harbor's ERP change. Determine overall and performance materiality when establishing the strategy.
- Plan risk assessment procedures
Develop an audit plan that includes procedures to understand Harbor's new ERP system and its effects on internal control. Risk assessment is part of the planned work, not something that must be finished before any strategy exists.
- Refine planning before further procedures
Use the risk assessment results to refine the strategy, including staffing, supervision, timing, and specialist needs. Plan the nature, timing, and extent of further audit procedures before performing them; Harbor's deadline does not reverse that order.
- Revise as information develops
Update the strategy, materiality, and audit plan when new information about Harbor's ERP system warrants changes. Planning is iterative: document significant changes to the strategy or plan and the reasons for them.
Key points
- Remember: preliminary activities come first; the current-year strategy and plan must guide further audit procedures, not follow them.
- A recurring client still requires current-year planning, even when the prior audit had no significant findings.
- Strategy, materiality, risk assessment, and detailed planning are interrelated, not a rigid sequence completed once.
How the exam traps you
- Roll forward last year's plan because the client is recurring. Address current-year preliminary activities and update planning for the new ERP system.
- Begin testing now and document planning later because the deadline is close. Resolve preliminary matters and develop planning that guides further audit procedures before performing them.
- Finish all risk assessment before establishing any audit strategy. Establish an initial strategy, plan risk assessment procedures, and refine planning using the results.
Question 2
Hint
Focus on what GAAS requires the auditor to have in place before moving ahead with audit work, especially when current-year facts differ from the prior year.
Answer D. AU-C 300 requires the auditor to plan the audit by establishing an overall audit strategy and developing an audit plan. Given the acquisition and new sales channel, Rivera must update the strategy and develop an audit plan that addresses those changed circumstances before performing further audit procedures. Planning is iterative and can be revised as new information emerges, but it must guide the work from the start.
Why not A: Planning should begin early and be adapted as the audit progresses; waiting for a final trial balance is unnecessary and contrary to GAAS, especially when changes increase the need for planning.
Why not B: Tempting because candidates may prioritize efficiency, but GAAS requires planning to guide the audit before further procedures are performed; the plan cannot merely be documented retroactively after problems are found.
Why not C: While prior-year planning information is useful, it must be updated for current-year changes. Significant events like an acquisition and a new sales channel require a revised strategy and plan at the outset rather than relying unchanged on last year's plan.
Question 3
Hint
Think about the difference between coordination items and audit steps whose value depends on unpredictability.
Answer A. Discussing routine coordination items (schedules, personnel availability, or the need for a specialist) is appropriate during planning. However, disclosing the exact timing of unpredictable procedures or the specific accounts to be tested would remove the unpredictability that helps detect or deter fraud and could enable management to conceal misstatements. Therefore, option C is least appropriate to discuss in detail.
Why not B: This relates to a high-risk area and resource planning, but discussing the use of a specialist does not reveal unpredictable test details and is generally appropriate during planning to ensure the audit team has needed expertise.
Why not C: Tempting because it involves planning details, but scheduling the delivery of working papers is a normal coordination activity that improves audit efficiency without impairing the auditor's ability to perform effective procedures.
Why not D: Arranging access to client personnel is routine coordination. While timing can be discussed broadly, specifying availability does not normally compromise audit effectiveness the way revealing unpredictable procedures would.
Question 4
Hint
Think about how the prior restatement, the new ERP implementation, and turnover in key financial personnel affect inherent and control risk, and how those risk changes should influence both performance materiality and the need for specialist involvement in planning.
Answer B. B is best because the prior restatement, new ERP implementation, management turnover, and significant accounting estimates increase inherent and control risks; these qualitative factors justify lowering performance materiality below the firm's usual 75% and adopting a primarily substantive strategy. An IT specialist is appropriate to evaluate IT general and application controls related to the new ERP, and assigning experienced staff with closer supervision helps reduce detection risk when engagement risk is elevated. Together these planning responses better ensure sufficient appropriate audit evidence.
Why not A: This option follows the firm's standard 75% practice and appears efficient, but relying primarily on controls and maintaining the prior performance materiality is inappropriate given the restatement, new ERP, and turnover in key financial personnel, factors that increase risk and weaken the basis for relying on controls without specialist evaluation.
Why not C: This distractor appeals to focusing on larger balances, but increasing materiality and relying mainly on analytics is inappropriate when risk is heightened (restatement, new ERP, management turnover, and complex estimates); higher risk requires more conservative materiality and more substantive evidence, not less.
Why not D: Although this option increases substantive testing, it fails to reduce performance materiality and omits an IT specialist despite a mid‑year ERP implementation that materially affects processing and controls; relying on mainly junior staff without greater supervision or specialist input may not adequately address the elevated risks.
Question 5
Hint
Focus on what the auditor should handle before getting too far into detailed planning, even for a long-standing client.
Answer D. AU-C planning guidance requires the auditor to perform preliminary engagement activities at the beginning of the current engagement, including evaluating compliance with ethical requirements (such as independence), considering client continuance, and determining whether engagement terms need revision or re-communication. Completing these steps early prevents the auditor from spending time on planning if the engagement should not continue or if key terms must be updated first.
Why not A: This is tempting because candidates sometimes assume continuance and ethical reviews apply only at initial acceptance. However, the auditor should consider continuance and independence at the start of each new engagement; a continuing relationship does not eliminate that requirement.
Why not B: While a change in scope can trigger a re-evaluation of engagement terms, independence, continuance, and whether engagement terms need refreshing should be considered at the start of every engagement, even without a scope change.
Why not C: A clean prior-year audit can make a client seem lower risk, but the absence of prior misstatements does not remove the requirement to perform preliminary engagement activities early in the current year.
Question 6
Hint
Focus on two separate planning ideas: whether changed circumstances in a recurring audit affect the engagement terms, and whether planning is fixed or iterative.
Answer A. For a recurring audit, the auditor does not automatically issue a new engagement letter every year, but should assess whether changed circumstances indicate that the terms should be revised or that the client should be reminded of them. Significant management and operational changes are exactly the kind of facts that trigger that consideration. Planning is also iterative, so the overall audit strategy and audit plan are revised as necessary as the engagement progresses.
Why not B: This is tempting because candidates often overfocus on whether the formal objective or reporting framework changed. However, GAAS requires the auditor to consider whether changes in management or the entity's operations make it appropriate to revise or remind the client of the engagement terms, even when the broad objective and framework stay the same. It is also too narrow to say only assertion-level procedures are affected, because the overall audit strategy may need revision as well.
Why not C: This distractor is attractive because the facts do create legitimate concern at the planning stage. But the rule is not that a new signed engagement letter is automatically required whenever management changes or assets move to a third party; the auditor must consider whether revision or reminder is appropriate. It is also wrong to treat the audit plan as essentially static unless a later deficiency appears, because planning should be updated proactively as risks and circumstances develop.
Why not D: A candidate might choose this by thinking the auditor should wait for evidence before changing the plan. But planning is performed before and during the audit, and the purpose of planning is to shape the nature, timing, and extent of procedures before substantive work is carried out. Deferring key planning changes until after substantive procedures reverses the proper sequence.
Common questions
What comes first in audit planning under AU-C 300?
Perform preliminary engagement activities, including continuance, ethical compliance, and establishing engagement terms. Harbor's deadline does not justify postponing these activities.
Does a recurring audit require a new engagement letter every year?
No. Consider whether circumstances require revised terms or a reminder of existing terms; a new letter is not automatically required annually.
Does risk assessment come before the overall audit strategy?
Not as a completed, separate phase. Establish an initial strategy and determine materiality, plan risk assessment procedures, then use the findings to refine the strategy and detailed audit plan.
Watch it solved
A full CPA AUD task-based simulation on Planning an Engagement, worked step by step.
Audit Planning: Materiality & Scoping | CPA AUD Simulation (TBS) on YouTube
Practice AUD like the real exam
The free ChatCPA simulator: real exam layout, timed testlets, starting with a question on this topic. No account needed to start.
Open the free simulator →More on Planning an Engagement
Questions from the ChatCPA bank of 17,658 CPA exam questions, each with a written reason for every wrong answer. ChatCPA is built by Nicholas Miller, CPA (Oregon #14907). How these pages are made. Spot an error? Tell us.