PracticeFARFree practice exam

FAR · Select transactions · 8 practice questions

ASC 606: Over Time vs. Point-in-Time Revenue Recognition

Revenue is recognized over time when any one ASC 606 criterion is met, but the no-alternative-use criterion also requires an enforceable right to payment. Below: follow the decision tree to separate over-time recognition from recognition when control transfers.

The ruleOne over-time criterion is enough: simultaneous receipt and consumption, customer control during creation or enhancement, or no alternative use plus an enforceable right to payment for performance completed to date. If none applies, recognize when control transfers.

Try one first

On January 2, Year 1, BuildCo enters into a contract to design and manufacture highly customized equipment for a customer for a fixed price of $900,000. The equipment is being built to the customer's unique specifications and has no alternative use to BuildCo. If the customer cancels the contract for reasons other than BuildCo's failure to perform, the contract gives BuildCo an enforceable right to reimbursement for costs incurred plus a reasonable profit margin for performance completed to date. Legal title and physical possession transfer only when the equipment is delivered at the end of Year 1. Assume the contract contains a single performance obligation, no variable consideration, no significant financing component, and that BuildCo can reasonably measure its progress toward completion. Under ASC 606, when should BuildCo recognize revenue?
Hint

Focus on whether any ASC 606 over-time criterion is met; legal title is relevant, but it is not always the deciding factor.

Decide it in order

  1. T1Does the customer simultaneously receive and consume the benefits as the entity performs?

    YesRecognize revenue over time. This criterion alone is sufficient.
  2. T2Does performance create or enhance an asset the customer controls as it is created or enhanced?

    YesRecognize revenue over time. Customer control during creation or enhancement is sufficient.
  3. T3Does the asset have no alternative use because of substantive, enforceable contractual restrictions or practical limits on redirection?

    NoRecognize revenue at a point in time when control transfers. None of the over-time criteria is met.
  4. T4If the customer cancels for reasons other than the entity's nonperformance, is payment for completed performance, including a reasonable profit, enforceable?

    YesRecognize revenue over time. Both no alternative use and the enforceable payment right are present.
    NoRecognize revenue at a point in time when control transfers. No alternative use alone is insufficient.

Key points

  • Remember: One criterion is enough, but the no-alternative-use route requires both no alternative use and enforceable payment rights.
  • No alternative use can reflect substantive, enforceable contractual restrictions on redirection or practical limits, including significant rework or economic loss.
  • Costs plus a reasonable profit support payment for completed performance; cost reimbursement alone fails in these machine contracts.
  • A logo or color change alone generally does not prevent redirection to another customer.

How the exam traps you

  • Choosing over time because customization prevents alternative use. Also require an enforceable right to payment for completed performance, generally costs plus a reasonable profit.
  • Waiting for delivery because legal title and physical possession transfer then. Test the over-time criteria first. Later title transfer does not defeat a criterion already met.
  • Treating progress billings or a nonrefundable deposit as proof of over-time recognition. Billing and deposits do not replace the over-time criteria or establish the required payment right by themselves.

7 more, each from a different angle

0 of 7 answered · 0 correct

Question 2

Ridge Co. enters into a contract in 20X5 to build a specialized addition onto a customer's existing warehouse. The addition is constructed on the customer's land, and the customer can direct approved design changes during construction. Ridge bills the customer monthly, but legal title to the completed addition will pass only at final acceptance. Ignoring collectibility issues, which factor governs whether Ridge should recognize revenue over time rather than at a point in time?
Hint

Focus on the ASC 606 criterion for over-time recognition that applies when work is being performed on the customer's property.

Question 3

On December 28, Year 1, Arden Co. entered into a contract to sell standard inventory to a customer for $48,000. The goods were complete and ready for shipment. The contract terms are FOB shipping point. Arden shipped the goods on December 29, Year 1, and the customer received them on January 3, Year 2. Assume collection is probable, the price is fixed, and Arden has no remaining performance obligations, customer-acceptance provision, or material return right. Under ASC 606, when should Arden recognize revenue from this sale?
Hint

Focus on the fact that determines when control passes from seller to customer, not on contract signing or cash receipt.

Question 4

Falcon Co. entered into two unrelated contracts in 20X6 to manufacture highly customized industrial units. For both contracts, Falcon has no practical ability to redirect the unfinished or finished unit to another customer, collectibility is probable, neither customer controls the asset as it is created, and the customer does not simultaneously receive and consume Falcon's performance. Contract 1: If the customer terminates for convenience, Falcon is entitled to payment for costs incurred to date plus a reasonable profit margin on work completed. Contract 2: If the customer terminates for convenience, Falcon is entitled only to reimbursement of specifically purchased raw materials; Falcon is not entitled to recover labor costs or any profit on work completed. Under ASC 606, how should Falcon recognize revenue for these contracts?
Hint

For the over-time criterion tied to customized assets, ask whether both required elements are present, not just one.

Question 5

Titan Co. enters into a contract in Year 1 to build a highly customized machine for Orion Corp. The machine is designed specifically for Orion and cannot be redirected to another customer without significant rework and loss. The contract provides that if Orion cancels for reasons other than Titan's nonperformance, Titan is entitled to recover its costs incurred to date plus a reasonable profit margin. No other goods or services are promised. Under ASC 606, which factor most directly governs whether Titan should recognize revenue over time rather than only when the machine is delivered?
Hint

Focus on the ASC 606 criteria for recognizing revenue over time, not on billing or title alone.

Question 6

Nova Manufacturing contracts to deliver a specialized packaging line for $4,800,000 plus a $200,000 bonus if the line is operational by September 30, 20X5. The contract covers design, equipment, installation, and testing; the customer cannot use the equipment apart from Nova's integration work, Nova's activities significantly integrate the items into one combined output, and the line is built to the customer's specifications with no practical alternative use to Nova. If the customer cancels for reasons other than Nova's nonperformance, Nova is entitled to reimbursement for costs plus a reasonable profit. Progress billings are made during construction, with the final 10% due after acceptance testing. Under ASC 606, what is the primary issue Nova must resolve to determine the contract's revenue recognition pattern?
Hint

Follow ASC 606's sequence: identify the performance obligation first, then decide timing; separate factors that affect 'when' from those that affect 'how much.'

Question 7

On January 1, Year 1, Able Co. entered into a contract to provide a single customized integration service for a fixed fee of $300,000 plus a $60,000 bonus if a specified regulatory approval is obtained. The contract contains one performance obligation satisfied over time, and Able measures progress using a cost-to-cost method that faithfully depicts performance. Through December 31, Year 1, Able concluded that none of the bonus should be included in the transaction price because the variable-consideration constraint was not met. By December 31, Year 1, Able had completed 50% of the performance obligation and recognized revenue accordingly. The regulatory approval was obtained on September 30, Year 2, and Able then concluded the full $60,000 bonus should be included in the transaction price. By December 31, Year 2, Able had completed 80% of the performance obligation. Assume no other changes in estimates and ignore financing effects. What is the most supportable amount of revenue Able should recognize in Year 2?
Hint

First determine the cumulative revenue that should be recognized by the end of Year 2 after the bonus becomes includable, then subtract the revenue already recognized in Year 1.

Question 8

On January 1, 20X5, Builder Co. entered into a contract to construct a warehouse on a customer's land for a fixed price of $3,000,000. The customer controls the land throughout construction, collectibility is probable, and Builder can measure progress reliably using a cost-to-cost input method. Assume there are no contract modifications, no variable consideration, and no significant financing component. When should Builder recognize revenue from this contract?
Hint

Focus on whether the customer obtains control of the asset during construction or only at the end.

Drill all 113 Revenue recognition questionsMixed across every rule in the topic, so you have to spot which one applies. That is how the exam does it.

Common questions

Is no alternative use enough for over-time revenue recognition?

No. That criterion also requires an enforceable right to payment for performance completed to date. If the payment requirement fails, check the other two criteria before concluding that recognition occurs at a point in time.

Does cost reimbursement create an enforceable right to payment under ASC 606?

Cost reimbursement alone fails the payment test in these machine contracts. Payment for completed performance generally must compensate the seller for costs incurred plus a reasonable profit, not merely reimburse materials or production costs.

Can revenue be recognized over time if title transfers at delivery?

Yes. Any one over-time criterion is sufficient, even when title and possession transfer later. A customized machine with no alternative use and an enforceable right to payment for completed performance qualifies.

Watch it solved

A full CPA FAR task-based simulation on Revenue recognition, worked step by step.

FAR Simulation: Revenue Allocation, Timing and Warranties ASC 606 on YouTube

Practice FAR like the real exam

The free ChatCPA simulator: real exam layout, timed testlets, starting with a question on this topic. No account needed to start.

Open the free simulator →

More on Revenue recognition

All Revenue recognition practice →

Questions from the ChatCPA bank of 17,658 CPA exam questions, each with a written reason for every wrong answer. ChatCPA is built by Nicholas Miller, CPA (Oregon #14907). How these pages are made. Spot an error? Tell us.