PracticeAUDFree practice exam

AUD · Assessing Risk and Developing a Planned Response · 6 practice questions

Audit Response to Midyear Control Failures

When exceptions undermine planned reliance, reassess affected assertions and reliance periods and obtain evidence through control testing, substantive procedures, or both. Below: judge responses to midyear overrides and remediation that does not prove earlier effectiveness.

The ruleWhen control exceptions undermine planned reliance, promptly reassess affected assertions and intended reliance periods, then obtain additional evidence through control testing, substantive procedures, or both. Remediation does not establish operating effectiveness before the repair.

Try one first

During the Year 2 audit of Orion Manufacturing, the auditor identified multiple control weaknesses: senior management emphasizes aggressive sales targets tied to large bonuses and the board meets infrequently; the internal audit function was disbanded in Year 1; the IT group makes application changes without formal authorization, testing, or documentation; monthly reconciliations are prepared by accounting staff who also post transactions and are not independently reviewed; and inventory counts are performed by warehouse staff who supervise the records. These problems affect several COSO components (control environment, monitoring, control activities, and information/communication). Considering COSO and the auditor's need to plan audit procedures, which of the following is the most appropriate planned response regarding reliance on internal controls and substantive procedures for inventory and revenue assertions?
Hint

Map each fact to the COSO components (especially control environment and monitoring); if multiple foundational components are weak, think about whether controls can reasonably be relied on or whether substantive procedures should be increased.

What should you do?

The situation

Trendline, a nonissuer, implemented an automated revenue-recognition control in January. The auditor planned reliance and reduced substantive procedures. September 30 testing found recurring manual overrides in July and August. Management reconfigured the control and documented remediation in October. Year-end is December 31. How should the auditor respond?

  1. Reassess now; revise reliance and procedures for affected revenue assertions and periods.

    Best Test October remediation before reliance. Address July and August separately; year-end control tests alone cannot establish earlier effectiveness.

  2. Avoid reliance for July and August; expand substantive testing for affected revenue assertions.

    Acceptable This can address the failure period, but reliance outside that period still needs evidence of operating effectiveness.

  3. Accept October remediation and retain the original reduced substantive plan.

    Wrong A documented repair does not prove effective operation during July and August or after remediation.

  4. Test the repaired control at year-end and rely on it for the entire year.

    Wrong Year-end effectiveness cannot establish that the control operated effectively during the earlier override period.

  5. Treat any control failure as requiring expanded substantive testing for the entire year.

    Wrong The response must follow reassessment of affected assertions and periods, not an automatic whole-year expansion.

Key points

  • Remember: A repaired control does not prove the control worked before the repair.
  • Scope the failures by revenue assertion and period before choosing additional audit procedures.
  • Additional control testing, substantive procedures, or both may provide the evidence needed to revise the reliance plan.

How the exam traps you

  • Treating documented remediation as proof that the original reliance plan remains valid. Test the repaired control before reliance and separately address the earlier failure period.
  • Using year-end control tests to prove July and August effectiveness. Obtain evidence that addresses the period when the overrides occurred.
  • Automatically expanding substantive testing for the entire year after any control failure. Determine which revenue assertions and reliance periods the failures affect before choosing additional procedures.

5 more, each from a different angle

0 of 5 answered · 0 correct

Question 2

During Year 2, a mid-size manufacturing client implemented a new ERP system that centralized purchasing, receiving, and accounts payable processing. Since implementation, the accounting manager can add vendors to the vendor master and approve vendor invoices for payment. Reconciliations among procurement, receiving, and accounts payable are routinely completed late and often require manual adjusting journal entries. Internal audit now reports administratively to the CFO rather than directly to the audit committee and has not performed independent post-implementation monitoring of the new ERP controls. Using the COSO framework to classify the weaknesses described, which of the following is the most likely effect on the auditor's planned response for the purchasing/accounts payable cycle?
Hint

First identify which COSO components the facts implicate (e.g., segregation of duties, monitoring), then consider how weaknesses in those components affect control risk and the extent of substantive testing.

Question 3

An auditor is performing interim procedures for Fenix Co. as of June 30, Year 1 (fiscal year‑end December 31, Year 1). Using the COSO framework and the auditor's professional guidance on fraud and internal control, the auditor planned most substantive testing at year‑end. During interim testing the auditor identified the following conditions. Which of these should prompt the auditor to expand substantive testing immediately (i.e., before waiting to perform additional work at year‑end)? Assume no other facts.
Hint

Which condition indicates the highest urgency because it suggests management override or possible fraud by senior personnel rather than routine control design or lower‑level operational issues?

Question 4

During the Year 2 integrated audit of Westbrook Manufacturing, the auditor identified control weaknesses in accounts payable. Facts: Westbrook has revenue of $120 million and net income of $6 million. The controller can create and modify vendor master records, initiate and approve vendor payments, perform the monthly bank reconciliation, and has system administrator privileges (including modifying user accounts and logs). The auditor discovered $2.0 million of unauthorized payments to a vendor owned by the controller; management reversed $0.2 million, and $1.8 million remained that required adjustment to the financial statements (the auditor considered this amount material). Monitoring by management (audit committee oversight and internal audit) is limited. Under the COSO framework and guidance on reporting control deficiencies, how should the auditor classify the identified internal control deficiency?
Hint

Focus on whether the deficiency allowed a material misstatement to occur and remain undetected by the company's controls during the period.

Question 5

During the Year 2 audit of Redstone Co., the auditor documents these revenue-cycle controls and conditions: (1) an ERP with barcode scanning at shipping automatically posts shipments and triggers revenue recognition when scanned; (2) the system enforces automated credit checks and a separate credit department makes credit approvals; (3) customer-master file changes require controller approval on paper, but multiple employees share a generic controller account to make those changes and changes are recorded under that generic ID; (4) IT applies system configuration changes without formal change-control or independent approvals; and (5) the board's audit committee meets quarterly and the CFO performs monthly A/R aging reviews for items > $10,000, but the CFO also approves write-offs and issues some credit memos. Using the COSO-based assessment of internal controls, what is the most appropriate auditor response regarding the planned nature, timing, and extent of substantive procedures for revenue transactions?
Hint

Identify which COSO components are weak (control activities and IT/information) and consider whether entity‑level controls can reasonably compensate when deciding whether to reduce substantive procedures.

Question 6

Client Co. implemented a new enterprise resource planning (ERP) system on July 1 of Year 2 that automated previously manual reconciliations and changed IT general controls. The audit team had relied on prior-year control testing and planned interim tests of controls on October 15 and substantive procedures at year-end (December 31). Management's monitoring activities reported no significant deficiencies since the implementation. In September the auditors learned the implementation deviated from plan (some process redesigns occurred) and two new accounting staff started in August. Considering COSO principles and the auditor's responsibility to reassess internal control, which timing/trigger response is most appropriate now?
Hint

Focus on whether the ERP implementation constitutes a significant change to control design/operation and whether prior‑year tests or management monitoring provide sufficient current evidence, such changes normally require updating understanding and retiming or performing new tests of controls.

Drill all 93 COSO questionsMixed across every rule in the topic, so you have to spot which one applies. That is how the exam does it.

Common questions

How should an auditor respond to recurring control overrides?

For Trendline's revenue, promptly reassess planned reliance and identify the affected assertions and periods. Determine whether additional control testing, substantive procedures, or both are needed.

Does remediation restore control reliance for the whole year?

No. Test the October repair before relying on it, and obtain sufficient evidence addressing the July and August failure period.

Can year-end control testing prove a control worked earlier?

Not by itself. Evidence that Trendline's repaired control works at year-end does not establish that it worked during July and August.

Practice AUD like the real exam

The free ChatCPA simulator: real exam layout, timed testlets, starting with a question on this topic. No account needed to start.