Control activities address risks; monitoring checks whether controls work; information and communication supplies needed information. Below, sort alternative observations about Elm Co.'s vendor bank-account change controls by purpose.

The ruleControl activities are procedures that address risks; monitoring evaluates whether controls work; information and communication supplies relevant, quality information to the people responsible for controls.

Try one first

During Year 2, Elm Co.'s internal audit department, reporting directly to the audit committee and with unrestricted access to records, performed regular evaluations of the design and operating effectiveness of key financial reporting controls, documented deficiencies, and tracked management's remediation until closure. Under the COSO internal control framework, which component is primarily addressed by these activities?
Hint

Decide whether the described work is implementing/performing controls or evaluating and reporting on their effectiveness over time.

Sort it

Control activities

Does it authorize changes, separate incompatible duties, or detect and correct unauthorized changes?

Monitoring

Does it evaluate whether controls work or follow up on identified control deficiencies?

Information and communication

Does it supply relevant, quality information to the people responsible for controls?

ItemGoes to
A weekly exception-report review identifies unauthorized vendor bank-account changes and requires corrections.Control activitiesThe review directly detects and corrects unauthorized changes rather than evaluating whether controls work.
The controller reviews recurring weekly exceptions to determine whether approval controls are failing and recommends fixes.MonitoringThe controller evaluates approval-control performance rather than merely correcting individual changes.
The exception report omits old and new bank-account details, with no other source available to the reviewer.Information and communicationThe supplied information cannot support the review. This is a report design problem.
Vendor bank-account changes require an authorized supervisor's approval before they take effect.Control activitiesAuthorization is the control itself, not an evaluation of that control.
Internal audit tests whether vendor bank-account changes received required approvals and reports control deficiencies.MonitoringInternal audit evaluates whether the approval control operates.
A complete exception report reaches the reviewer only after the scheduled review.Information and communicationRelevant information arrives too late to support the scheduled control.
The employee who changes vendor bank details also approves those changes, without independent review.Control activitiesIncompatible duties are not separated. The weakness is in the control's design.
Management does not evaluate whether vendor-change approval controls remain effective after system implementation.MonitoringThe missing step is evaluation of continuing control effectiveness.
The system routes vendor bank-account change exceptions to the employee responsible for reviewing them.Information and communicationRouting delivers relevant information to the person who must act on it.
The system lets unauthorized employees approve bank-account changes despite the communicated approval policy.Control activitiesActual permissions do not enforce the policy. Communicating the policy does not implement the approval control.
Management tracks identified vendor-change approval-control deficiencies until corrective actions are complete.MonitoringFollow-up addresses identified failures in controls.
Management sends the revised vendor-change approval policy to employees who process those changes.Information and communicationSending the policy communicates control responsibilities. It does not itself approve changes.

Key points

  • Remember: Ask whether the action performs a control, evaluates that control, or supplies information for that control.
  • Weekly work can be monitoring when it evaluates whether approval controls function.
  • A communicated approval policy does not fix a system that permits unauthorized approvals.

How the exam traps you

  • Calling every recurring review monitoring. Ask whether Elm is detecting unauthorized changes or evaluating whether its approval controls work.
  • Calling missing report fields a failure to perform the review. When needed details have no other source, classify the report design weakness as information and communication.
  • Treating a communicated policy as an effective approval control. Inspect the system's actual permissions; unauthorized approval access is a control activities weakness.

5 more, each from a different angle

0 of 5 answered · 0 correct

Question 2

During walkthroughs of the inventory cycle, an auditor learns that warehouse employees regularly identify damaged and obsolete inventory, but there is no formal process for communicating those issues to accounting. As a result, inventory write-downs are often not recorded until year-end. Assume physical safeguards and approval controls over inventory adjustments already exist. Under the COSO framework, which action would best address this weakness?
Hint

Focus on which COSO component is failing: the issue is not detecting damaged goods, but getting that information to the right people in time.

Question 3

In obtaining an understanding of internal control, an auditor learns that each month the controller compares actual operating results with the approved budget, investigates significant variances, and documents follow-up on unusual differences. Under the COSO framework, what is the correct treatment of this monthly review?
Hint

Ask whether the procedure is a specific control being performed or an evaluation of whether controls in general are working.

Question 4

During an auditor's walkthrough of the purchasing and cash disbursements cycle, the auditor learns that the accounts payable supervisor can add new vendors to the master file, enter invoices, and release electronic payments. Management asks which action would best strengthen internal control under the COSO framework. Assume the company has enough personnel to reassign duties. Which action is best?
Hint

Focus on which COSO response most directly addresses the specific risk created by one employee performing incompatible duties.

Question 5

As part of obtaining an understanding of internal control, an auditor learns that Maple Co. implemented a new billing system in Year 1. Since implementation, the controller has reviewed weekly exception reports, investigated recurring processing errors, and recommended changes when existing controls were not operating as intended. Assuming the underlying reports are already being produced by the system, which COSO component is most directly illustrated by the controller's actions?
Hint

Focus on whether the facts describe designing/perfoming a control, identifying risks, communicating information, or evaluating whether controls continue to work.

Question 6

In obtaining an understanding of internal control over revenue, an auditor learns the following about a company that launched a new online discounting platform in Year 2: - Before launch, management documented sales objectives, identified the risk of unauthorized discount overrides, considered fraud incentives created by a new volume-bonus plan, and evaluated how the new platform changed the company's risk profile. - The revised approval matrix was formally communicated to sales operations and IT before go-live. - Internal audit reviews weekly exception reports of discount overrides and follows up on unusual items. - Despite those steps, the system was left configured so that any regional sales manager could approve discounts above the board-authorized threshold. Assume these facts are complete and no broader tone-at-the-top or personnel-competence issues were noted. Under the COSO framework, in which component is the primary deficiency?
Hint

Separate the step of identifying and analyzing a risk from the step of designing and implementing the control response to that risk.

Drill all 93 COSO questionsMixed across every rule in the topic, so you have to spot which one applies. That is how the exam does it.

Common questions

What is the difference between COSO control activities and monitoring?

A review that detects and corrects unauthorized vendor bank-account changes is a control activity. A review that evaluates whether approval controls work is monitoring.

Which COSO component covers missing information in an exception report?

Information and communication. Elm's report omits needed bank details and offers no alternative source, so its design does not support the review.

Does a weekly control review count as COSO monitoring?

Frequency does not decide the classification. Elm's weekly review is monitoring when its purpose is to identify failing approval controls, not simply to detect unauthorized changes.

Practice AUD like the real exam

The free ChatCPA simulator: real exam layout, timed testlets, starting with a question on this topic. No account needed to start.

Open the free simulator →

More on COSO

All COSO practice →

Questions from the ChatCPA bank of 17,658 CPA exam questions, each with a written reason for every wrong answer. ChatCPA is built by Nicholas Miller, CPA (Oregon #14907). How these pages are made. Spot an error? Tell us.