Mailbox Rule: Acceptance and Revocation Timing

Authorized acceptance normally takes effect when sent unless the offer requires receipt; revocation takes effect when received. Follow one consulting offer through a timeline, then compare the result when only the offer's receipt requirement changes.

The ruleAuthorized acceptance normally takes effect on dispatch, but an express receipt requirement overrides that default. Revocation takes effect on receipt.

Try one first

On May 1, Lane sent Baker a written offer to hire Baker to perform consulting services for $8,000. The offer stated that Baker could accept by mail no later than May 10. On May 4, Lane mailed a revocation of the offer. Before receiving that revocation, Baker mailed an unconditional acceptance on May 5. Baker received Lane's revocation on May 6. Assuming common-law contract rules apply and no option contract exists, which statement is correct?
Hint

Focus on which communication is effective when sent and which is effective only when received.

The timeline

  1. May 1Lane sends Baker an $8,000 consulting offer stating, "You may accept by mail no later than May 10."

    Receipt-required version: Lane instead states, "Your mailed acceptance must be received by May 10." Every other fact stays the same.

  2. May 4Lane mails a revocation.

    Neither version is revoked yet. Mailing does not make a revocation effective.

  3. May 5Before receiving the revocation, Baker mails an unconditional acceptance.

    Original offer: a contract forms today. Receipt-required version: mailing is not effective acceptance, so no contract forms today.

  4. May 6Baker receives Lane's revocation.

    Original offer: the revocation is too late. Receipt-required version: the revocation terminates the offer before acceptance becomes effective.

  5. May 11Lane receives Baker's acceptance, after the May 10 deadline.

    Original offer: late arrival does not undo the May 5 contract. Receipt-required version: no contract forms; the May 6 revocation already terminated the offer.

Key points

  • Remember: A receipt requirement changes which date controls, not the date the acceptance was mailed.
  • Compare effective times, not which letter was mailed first.
  • Keep the sender straight: Baker sends acceptance; Lane sends revocation.

How the exam traps you

  • Treating Lane's May 4 mailing as an effective revocation. Revocation takes effect when Baker receives it on May 6.
  • Applying dispatch timing despite an express receipt requirement. Under the changed offer, Baker's May 5 mailing does not form a contract.

5 more, each from a different angle

0 of 5 answered · 0 correct

Question 2

Harper mailed Lane a signed offer on May 1, Year 1, to repaint Harper's house for $18,000. The offer stated: "You may accept only by signing this offer and returning it by mail. Your acceptance must be received by me no later than May 10, Year 1." On May 8 Harper mailed a revocation. On May 9 Lane signed the offer and mailed his acceptance. Lane received Harper's revocation on May 10. Harper received Lane's acceptance on May 11. Assume no option contract, no reliance, and general common-law contract rules apply. Which conclusion is best supported?
Hint

First determine whether the offer changes the default mailbox rule (dispatch vs. receipt); then apply the rules for when revocations and acceptances become effective.

Question 3

On March 1, Owner signed a written agreement giving Buyer the exclusive right to purchase Owner's warehouse for $800,000 at any time until 5:00 p.m. on March 10. Buyer paid Owner $2,000 on March 1 for that right. The agreement did not specify a method of acceptance. On March 9, Buyer placed a properly addressed written acceptance in the mail. On March 10, before receiving anything from Buyer, Owner called Buyer and stated that Owner was revoking because a third party had offered a higher price. Owner received Buyer's mailed acceptance on March 11. Assume common-law contract principles apply and there is no statute of frauds issue. Which conclusion is best supported?
Hint

First determine whether Buyer's payment created an option that made the offer irrevocable. Then consider under common‑law principles whether exercising an option is typically effective on dispatch or instead requires receipt.

Question 4

Owner mailed Contractor an offer on June 1 for remodeling services at Owner's office building and stated that the offer would remain open until June 10. Contractor received the offer on June 3. No consideration was paid to keep the offer open. On June 4, Contractor mailed a rejection. On June 5, Contractor changed its mind and sent an acceptance by overnight courier. Owner received the acceptance on June 6 and received the rejection on June 7. Under common law contract rules, which is the best conclusion?
Hint

Focus on two separate timing issues: whether common law or UCC rules apply, and whether the offeree sent a rejection before sending the acceptance.

Question 5

On June 1, Seller mailed Buyer an offer to sell a machine for $40,000, stating that the offer would remain open until June 10. Buyer paid no consideration to keep the offer open. Assume the offer did not require receipt of acceptance and Seller did not revoke the offer. Buyer received the offer on June 3, mailed a rejection on June 4, then changed its mind and mailed an acceptance on June 5. Seller received the acceptance on June 6 and received the rejection on June 7. Which conclusion is best supported?
Hint

Focus on the effect of sending a rejection first and an acceptance later, and ask which communication became effective first.

Question 6

Gray Corporation emailed Lane Consulting an offer for a six-month software implementation project for $90,000. The offer stated: "You may accept only if I receive your signed acceptance email at this email address by 5:00 p.m. on June 10. No other method of acceptance will be effective." Before 5:00 p.m. on June 10, Lane left Gray a voicemail stating that Lane accepted and mailed a signed letter of acceptance. Lane did not send any acceptance email. Assume common-law contract principles apply, and there is no waiver, estoppel, or reliance issue. Which response was required for Lane to create a binding contract?
Hint

Start with the offer's own instructions. General acceptance rules usually apply only when the offer does not make one method exclusive.

Drill all 126 Contracts questionsMixed across every rule in the topic, so you have to spot which one applies. That is how the exam does it.

Common questions

When is acceptance effective under the mailbox rule?

For Lane's offer allowing acceptance by mail, Baker's authorized acceptance takes effect when mailed on May 5. A contract forms before the revocation arrives.

Can an offer require acceptance to be received?

Yes. If Lane requires receipt by May 10, Baker's May 5 mailing is not enough. Lane's revocation arrives May 6 before the acceptance arrives May 11, so no contract forms.

When does a mailed revocation become effective?

Lane's revocation takes effect on receipt, not mailing. Under the original offer, it arrives too late to undo the contract formed on May 5.

Practice REG like the real exam

The free ChatCPA simulator: real exam layout, timed testlets, starting with a question on this topic. No account needed to start.

Open the free simulator →

More on Contracts

All Contracts practice →

Questions from the ChatCPA bank of 17,658 CPA exam questions, each with a written reason for every wrong answer. ChatCPA is built by Nicholas Miller, CPA (Oregon #14907). How these pages are made. Spot an error? Tell us.