PracticeAUDFree practice exam

AUD · Ethics and Professional Responsibilities and General Principles · 9 practice questions

AU-C 230: Audit File Changes After the Completion Date

After the documentation completion date, auditors may add explanations but may not delete or discard existing documentation during retention. Follow an omitted revenue cutoff memo from discovery to a properly documented late addition.

The ruleAfter the documentation completion date, retain existing audit documentation until the retention period ends. Clearly identify necessary late additions and document the specific reason, when they were made and reviewed, and by whom.

Try one first

A CPA firm completed a Year 1 audit under AICPA GAAS. The auditor's report was released on March 15, Year 2. On May 20, Year 2, the engagement partner considers the following changes to the audit file: 1. Add a memo clarifying how the team resolved an inventory pricing issue, and document the reason for the addition, the date added, and who prepared and reviewed it. 2. Remove an original revenue cutoff testing workpaper because a clearer reformatted version covering the same testing has now been added to the file. Assume both items relate to matters considered during the audit and the firm's documentation retention period has not expired. Which conclusion is best supported?
Hint

Work separately through two questions: Has the documentation completion date passed, and are additions treated the same as deletions after that date?

Step by step

  1. Confirm the file is complete

    For a nonissuer audit under AU-C 230, final file assembly ended April 20. On July 10, an internal inspection finds an omitted revenue cutoff memo; the retention period has not expired.

  2. Confirm the work already occurred

    The cutoff testing, resolution, and final memo were completed before report release. No new procedures are needed, and the report remains unchanged.

  3. Retain the earlier draft

    An earlier draft memo describing the cutoff issue as unresolved remains in the completed file. Do not delete it during the retention period, even if the partner approves.

  4. Add without replacing

    Add the omitted final memo as a clearly identified post-completion addition. Keep the earlier draft intact rather than overwriting it or substituting the final memo.

  5. Explain the specific reason

    Record that the final memo was inadvertently omitted during assembly and is being added to document the cutoff resolution. The unchanged conclusion does not eliminate this requirement.

  6. Record dates and responsible people

    Record July 10 as the actual addition date, identify who made and reviewed the addition, and record when the review occurred. Do not make the addition appear to have been in the file on April 20.

Key points

  • Remember: Add the missing explanation, not a replacement that erases the original.
  • Keeping the unresolved draft preserves history; it does not reverse the final cutoff conclusion.
  • The memo's original preparation date does not establish when it entered the assembled file.

How the exam traps you

  • Discarding the draft because the final memo supersedes it. Keep the draft and add the final memo without replacing existing documentation.
  • Skipping the reason because the audit conclusion is unchanged. Document the specific reason for the addition, plus when and by whom it was made and reviewed.
  • Making the late addition appear to have been present at file completion. Record the actual addition date; do not conceal when the memo entered the file.

8 more, each from a different angle

0 of 8 answered · 0 correct

Question 2

An auditor released the audit report on a client's Year 1 financial statements. Seventy-five days later, during an internal inspection, the engagement partner discovers that the file does not include a memo summarizing a required discussion with management that occurred before report release, although contemporaneous emails and meeting notes created at that time support that the discussion occurred. The partner also notices that a preliminary planning checklist, later superseded by a final signed checklist, was left in the file. Assume no new audit procedures are being performed, no new facts arose after report release, and the retention period has not expired. Under AICPA (AU-C 230) engagement documentation requirements, which response is most appropriate?
Hint

Distinguish the report release date, the AU-C 230 documentation completion date (60 days after release), and the retention period; then decide whether each proposed action is an addition that requires documentation or a deletion that is prohibited.

Question 3

An auditor of a nonissuer under AICPA GAAS has reached the documentation completion date. Assume any omitted item, if later added, is supported by contemporaneous records and relates to work actually performed before the report release date unless a choice states otherwise. Which situation requires the heightened post-report-date documentation AU-C Section 230 describes for exceptional circumstances, rather than only ordinary late-file documentation of the reason for the change and who and when made and reviewed the change?
Hint

Ask whether the auditor is performing new or additional audit procedures after the report date, or merely adding documentation of work performed before that date.

Question 4

Assume the engagement is subject to AICPA audit documentation requirements. An auditor released an audit report on June 1, Year 2. On August 20, Year 2, the audit manager discovers that a copy of an executed debt covenant agreement, which had been obtained and used during fieldwork before report release, was inadvertently omitted from the final engagement file during assembly. No new facts have arisen since report release, and no new audit procedures are needed. What is the correct treatment?
Hint

First determine whether the discovery occurs before or after the documentation completion date. Then ask what the standards allow for adding existing evidence after that date.

Question 5

A CPA firm completed final assembly of a nonissuer audit file on Day 50 after the report release date. On Day 75, the engagement partner discovers that a memorandum prepared before the report's release, documenting the team's rationale for a significant accounting estimate, was inadvertently omitted from the assembled file. The file also still contains an earlier draft schedule with errors that had been superseded before the report was released. No new audit procedures are being performed. Under AICPA AU-C 230, which action is most appropriate?
Hint

Treat this as two questions: what may be added to an assembled file after final assembly, and what may be removed or discarded after final assembly.

Question 6

In a nonissuer audit performed under AICPA auditing standards, the auditor completed assembly of the final engagement file within the required period after the report release date. Two months later, the engagement partner adds a memorandum to clarify why a sample size was expanded during inventory testing. Assume no new audit procedures were performed, no conclusions changed, and the addition is only to better explain work already performed. Which action is most appropriate?
Hint

Focus on what the standards require when documentation is changed after the file completion date, even if the change only clarifies work already performed.

Question 7

Assume a nonissuer audit performed under AICPA auditing standards. The auditor released the report on March 1, Year 2. On May 20, Year 2, after the engagement-file assembly completion date, the engagement partner discovers that the final file does not include the memorandum that concluded a significant revenue cutoff exception was resolved. The underlying shipping documents supporting that conclusion were already in the file before report release, but the concluding memorandum and evidence of manager review are missing. An earlier memorandum describing the cutoff issue as unresolved remains in the assembled file. The partner proposes to add the missing concluding memorandum now, insert review documentation as though it had been present before report release, and remove the earlier unresolved memorandum to avoid confusion. Which conclusion is best?
Hint

Refer to AU-C 230: late additions are permitted if the file records the reason, date, preparer, and reviewer; prohibited actions include deleting prior documentation, backdating, or making late entries appear original.

Question 8

Assume this is a nonissuer financial statement audit performed under AICPA auditing standards only. The auditor dated the report March 1, Year 3, and completed assembly of the final engagement file on April 20, Year 3 (the documentation completion date). On August 20, Year 3, the engagement partner discovers that one workpaper lacks documentation of who reviewed it and another workpaper does not document why an unusual inventory exception was resolved without a proposed adjustment. Team members state that both matters were addressed before the report date and can be explained orally and by contemporaneous emails. Which conclusion is most appropriate regarding the engagement documentation?
Hint

Consider AU-C 230: are additions after the documentation completion date allowed, and what does the standard say about removing existing documentation?

Question 9

In an audit of a nonissuer performed under U.S. GAAS, the auditor dated the report March 8, 20X6. The auditor delivered the auditor's report and audited financial statements to management on March 15, 20X6, thereby granting permission to use the report. On June 1, 20X6, the engagement partner discovered that a memorandum documenting a significant consultation that occurred before the report date had been omitted from the assembled audit file. No additional audit procedures are needed, and no law or regulation imposes a shorter documentation deadline. Within what period should the final audit file have been assembled, and what is the proper treatment of the omitted memorandum?
Hint

Identify the event that starts the GAAS documentation-completion clock, then ask whether a post-completion change is prohibited entirely or simply subject to documentation requirements.

Drill all 95 Requirements for Engagements Documentation questionsMixed across every rule in the topic, so you have to spot which one applies. That is how the exam does it.

Common questions

Can auditors delete draft workpapers after the documentation completion date?

No. If the draft remains in the completed file, retain it through the applicable retention period, even when a final memo supersedes it.

What must be documented for a late addition under AU-C 230?

Document the specific reason for the addition and when and by whom it was made and reviewed. Identify it as a late addition rather than making it appear original.

Does adding an omitted audit memo require reissuing the report?

Not in this scenario. The cutoff work and conclusion predate report release, no new procedures are needed, and the memo does not change the report.

Practice AUD like the real exam

The free ChatCPA simulator: real exam layout, timed testlets, starting with a question on this topic. No account needed to start.

Open the free simulator →

More on Requirements for Engagements Documentation

All Requirements for Engagements Documentation practice →

Questions from the ChatCPA bank of 17,658 CPA exam questions, each with a written reason for every wrong answer. ChatCPA is built by Nicholas Miller, CPA (Oregon #14907). How these pages are made. Spot an error? Tell us.